Fourth Avenue Bridge
Monday, December 31, 2001
WHERE WE ARE
Originally published 20011231
Originally published December 24, 2001
Pile driving for span 3 of the work trestle is completed.
Sidewalks are poured for intersection improvements at Fourth Avenue and Perry Street and Harrison Avenue and Perry.
THIS WEEK
No bridge demolition is scheduled until after Christmas Day. Work also will resume on the work trestle after Christmas.
[an error occurred while processing this directive]
The Olympian Copyright 2001
back to main Fourth Avenue Bridge index |