Fourth Avenue Bridge Monday, January 14, 2002

BRIDGE UPDATE

Originally published Monday, January 14, 2002

WORK IN PROGRESS

Crews demolished one of the houses at the future site of the Park of the Seven Oars last week.

Workers will continue building a work trestle and installing water lines this week. Crews will install crosswalk signs on Fifth, Fourth and Harrison avenues in preparation for a detour.

The work trestle will be ready for use this week. Water line work is scheduled to wrap up Friday. A traffic detour is scheduled to begin Jan. 29.