BRIDGE UPDATE
Originally published Monday, January 14, 2002
WORK IN PROGRESS
Crews demolished one of the houses at the future site of the Park of the Seven Oars last week.
Workers will continue building a work trestle and installing water lines this week. Crews will install crosswalk signs on Fifth, Fourth and Harrison avenues in preparation for a detour.
The work trestle will be ready for use this week. Water line work is scheduled to wrap up Friday. A traffic detour is scheduled to begin Jan. 29.