Fourth Avenue Bridge
Monday, January 21, 2002
BRIDGE UPDATE
Originally published Monday, January 21, 2002
RIGHT NOW
Construction crews are working to install utility lines on west Fourth Avenue, between Olympic Way and West Bay Drive. Work requires the closure of west Fourth Avenue, between Olympic Way and Sherman Street.
WHAT'S NEXT
Contractor will continue to construct the work trestle.
LONG TERM
A second crane will install coffer dams for the construction of new bridge piers. The contractor plans to pave Fourth Avenue between Olympic Way and West Bay Drive on Jan. 28 or 29. The contractor must re-stripe the roadway prior to implementing a detour Feb. 5.
The Olympian Copyright 2002
back to Fourth Avenue Bridge index |