Fourth Avenue Bridge
Monday, February 18, 2002
BRIDGE UPDATE
Originally published Monday, February 18, 2002
FRIDAY
Construction crews worked on the temporary work trestle and coffer dams.
NEXT
Crews will continue building a storm line along West Bay Drive and Harrison Avenue and an access road to construct a tie-back wall along Olympic Way.
LONG-TERM
Crews will continue to build the work trestle, coffer dams and sewer line along Olympic Way and West Bay Drive. Crews will also begin excavation for a pier at the west end of the bridge below Olympic Way.